03 December 2008
) Opinion of IFA on the Connected Transections
2007 244,448 2012 503,028
2008 288,665 2013 567,074
2009 336,843 2014 636,178
2010 388,851 2015 710,671
Source : Thai DCI Engineering Consultant Co., Ltd. and Thai Tap Water Supply
Plc.
The Company's water distribution volume in 2008 is in line with that in the
finding by Thai DCI as in the above table. Although its average distribution
volume is still lower than its full capacity, to be aligned with its business
operation plan, the Company has submitted a request to expand its production
capacity by another 100,000 cu.m./day for PWA's consideration since 2006 in
order that it would be able to produce tap water to adequately serve the
consumers' demand in the future. To accommodate the production capacity
expansion, beside using the existing infrastructures, the Company needs
construction of water pressure enhancement stations to solve water
distribution problems. Tap water production under the expansion project is
anticipated to start around 2010.
3.2 Advantages and disadvantages between making and not making the transaction
which will have impacts on the Company
Advantages of making the transaction
1. The Company's earning of income from water sales under the expansion
project in the volume up to 100,000 cu.m./day amounting to Bt. 12,669.40
million - Bt. 13,564.75 million
According to the Company's Information Memorandum on a connected
transaction submitted to the SET on October 24, 2008, the Company is now
under negotiation on the conditions of the PSA with PWA and is awaiting the
PWA Board's consideration result of relevant issues to the PSA. Under the PSA,
PWA will purchase tap water supply from the Company by an additional volume of
up to 100,000 cu.m./day. On October 30, 2008, the IFA had a meeting with the
Company's top executives thereby it was informed that the PSA for the
expansion project to raise the production capacity was under the drafting
process of PWA. The draft PSA is expected to be available to the Company
around December 2008. The Company's executives said that the new PSA would
have salient points similar to those of the existing one (as detailed in
summary of salient points of the existing PSA in the annual disclosure form:
form 56-1 for 2007 in section 2 page 211).
In view of the above, if the PSA is made between the Company and PWA, the
Company will be able to earn income of a total of Bt. 12,669.40 million - Bt.
13,564.75 million from distributing tap water throughout the contract term of
around 24 years (under assumption that the PSA will expire on July 20, 2034)
as detailed in 4.1.2. This source of income will help boost the Company's cash
flows, net profit and earning per share. Thus, this production capacity
expansion will be a benefit to the Company and its shareholders.
2. The Company's maintaining of its leadership status being the largest
private provider of water service in Thailand
The expanded production capacity up to 100,000 cu.m./day when combined the
existing production capacity of 320,000 cu.m./day (in practice, the Company
can raise production capacity to 340,000 cu.m./day as maximum) and plus PTW's
production capacity of 388,000 cu.m./day (former production capacity of
288,000 cu.m./day plus expanded capacity of 100,000 cu.m./day) will make the
Company have a total production capacity of 808,000 cu.m./day, which would be
far higher than that of Universal Utilities Co., Ltd., the second largest
private provider of water service with total capacity of 186,000 cu.m./day and
Ekcomtara Co., Ltd., the third largest with capacity of 36,000 cu.m./day.
Hence, if the Company does not raise its production capacity this time, there
may be new entrants to produce and distribute tap water supply to meet the
increasing demand the Company is unable to fulfil.
3. The Company employing efficient and modern technology
In the construction for the expansion of capacity, the contractor will be
engaged to use the standard agreement of the International Federation of
Consulting Engineering ("FIDIC") in respect of both civil construction and
electrical and mechanical works. Thai MM Co., Ltd. ("Thai MM") will be engaged
as the engineer in the project management and construction supervision
handling all the project management including engineering design using the
updated technology. Such technology includes the under drain filtration system
which is a state-of-the-art offering the highest filtering speed among its
kind in Thailand. The Company is the country's first tap water producer using
such technology. In addition, under the expansion project, the Company will
have the SCADA (Supervisory Control and Data Acquisition), which is a water
distribution control system, moved to be installed at the bulk transmission
main enhancement
plant 1 (BP1), which will allow for higher efficiency in water distribution
management. Earlier, the water distribution system was integrated to the water
production system. The SCADA will calculate water volume in the water tank in
each station and control the water transmission and distribution to all the
stations with better precision and punctuality. Thus, the Company will be
able to maintain its cost in the implementation with maximum efficiency and
with the minimum fluctuations, especially as compared with the existing tap
water production and distribution system.
Disadvantages of making the transaction
1. Liquidity and sources of funds
From interviews with the Company's executives, for the expansion project, the
Company has planned to make borrowing from financial institutions and use its
own working capital from the operations. However, borrowing from financial
institutions, either at home or overseas, would be accompanied by strict
provisions and commitments under the current circumstances, hence the Company
may not get sufficient credit lines for its project implementation and/or it
may have to pay higher interest rates than before. Also, it would be harder
for the Company to achieve its target of relief of financial burden by
reduction of interest payment by at least 0.5%. If the Company borrows Bt. 650
million (about 50% of total project cost), the total liabilities to equity
ratio of the Company will go up from 1.16 times as of September 30, 2008 to
1.24 times. In this regard, if the Company has to rely on its own working
capital for the construction under the expansion project (in case borrowing
from financial institutions is inadequate for the project implementation), the
Company may be exposed to liquidity and financial problems. It may risk
failing to pay dividend to the shareholders in the future. This would be the
case despite the fact that the Company just raised funds through the capital
market by initial public offering in May 2008.
2. Water consumption volume in the service areas may not come out as
projected when the Company becomes operational, hence possible
lower-than-expected rate of return.
Advantages of not making the transaction
The Company will be able to pursue for the achievement of its financial burden
relief target through reduction of interest payment at least 0.5% and to pay
dividend to the shareholders due to no borrowing of loans from financial
institutions.
Disadvantages of not making the transaction
1. Cost of project study and cost of land for the construction of two bulk
transmission main enhancement plants
Although the engagement of CK to carry out the civil construction will take
place only when the Company has been approved by PWA to enter into a PSA, as
this production capacity expansion project requires high investment cost of
Bt. 1,300 million, there must be preparations in various respects starting
from 2006, such as engagement of a consultant in the work preparation,
engagement of consulting engineer in project management, purchase of land for
construction of water pressure enhancement stations and deployment of part of
the personnel in
project coordination and implementation. The initial expenditure for such
preparation as informed by the Company is expected to be in a total of Bt. 238
million, which would be a waste if the Company is eventually unable to enter
into the transaction.
3.3 Advantages and disadvantages of making the transaction with a related
party compared with making the transaction with an outside party
Advantages of making transaction with a related party
Thai MM as the project manager has considered various construction
circumstances and timelines for the whole project. It has recommended
engaging two turnkey contractors, one in civil construction and the other in
mechanical and electrical works. Both contractors are EPC contractors
responsible for engineering, procurement and construction until the project
completion according to the agreement. At the same time, to inspect and
ensure compliance with the agreement, the Company may have to engage an
independent engineer under the comment by PWA. The preliminary structure of
the project management is as below:
Preliminary structure of project management
PWA TTW
| |
| |
Independent Engineer <-----------> Project Manager
Thai MM
________|__________
| |
| |
M&E Contractor Civil Contractor
In July 2008, the Company invited potential contractors with expertise in
mechanical, electrical and civil works and standard work credentials to join
in the proposal of services for the contract works. There were altogether nine
prospective parties. In September 2008, two out of three final prospective
parties (comprising two mechanical and electrical contractors and one civil
contractor) submitted their proposals. The result of the proposal
consideration has come out that the winner for mechanical and engineering
works is S.Napa (Thailand) Co., Ltd., which is not a connected party as stated
in the Information Memorandum submitted to the SET. CK is the civil
contractor. Despite CK being a related party, there are advantages engaging CK
as the civil
contractor as follows:
1. CK is the country's leading contractor for large infrastructures with
dependable experience both domestically and overseas
CK has engaged in contractor business in Thailand for over 35 years. It is
one of the few local contractors that can handle sophisticated construction
projects with the use of high technology, such as large scale infrastructure
projects. Besides, CK has all along developed its engineering and management
capabilities. It has thus been able to handle projects on a turnkey basis for
concession projects, which are in the nature of Build,
Transfer and Operate (BTO), Build, Operate and Transfer (BOT), Build, Own
and Operate (BOO) and Acquire, Operate and Transfer (AOT) concession for
large, medium and large projects. CK's past credentials are, for example,
Bangna-Chonburi expressway, Bangkok International Airport development project,
construction of building and parking for Bangkok Metro Co., Ltd. ("BMCL"),
Bangphon-Suksawat (Bangphli-Bang Khun Thian) project, MRTA Chaloem
Ratchamongkhon metro line by BMCL, power generation for EGAT, Nam Ngum 2
hydro-power plant in Lao People's Democratic Republic, etc.
2. CK undertook the construction of the extension of tap water production and
distribution plant in the volume of 100,000 cu.m./day for PTW and the existing
water production plant of the Company
CK started its construction of the extension of tap water production and
distribution plant in the volume of 100,000 cu.m./day for PTW in February 2006
(total construction value was Baht 693.1 million, information from the
Company's prospectus). The new plant started water distribution to PWA on
August 1, 2008. PTW's water production capacity has then become 388,000
cu.m./day. In addition, CK was the contractor for the Company's existing water
production and distribution plant in its business start-up year in 2000. In
view of this, CK can be regarded as a contractor with knowledge in the
Company's existing water production plant infrastructures. This can ensure its
capabilities to handle and complete the construction work according to the
contract timeframe.
3. CK has firm financial standing and sound past operational performance,
hence low risk of late construction work completion and delivery
The Company will make payment for the civil construction in an amount up
to Bt. 640 million (excluding VAT) to CK. Payment will be in installments by
work progress starting from the contract date designated by December 2008 or
after the approval of the shareholders' meeting. Construction period is around
18 months (January 2009-June 2010). Such payment amount is considered rather
high. However, there is low risk of CK's failure to complete the construction
according to the agreement. This is because CK has firm financial status and
its operating results during 2007-quarter 3 of 2008 were favorable compared
with other contractor companies listed on the SET. CK recorded total revenues
in 2007 and quarter 3 of 2008 of Bt. 14,918 million and Bt. 10,568 million,
with net profit of Bt. 33 million and Bt. 570 million respectively. Under the
current circumstances, it is rathe difficult to seek to engage any other
contractor with firm financial condition and high expertise in the
construction in this field like CK.
Disadvantages of making transaction with a related party
Making a transaction with a related party may raise doubt whether
negotiations on prices andconditions as well as payment method have been made
at artm's length.
Necessity for making the transaction with related party and reasons form not
making with outside party
In making this transaction, when taking into account the past
experience and top-rank expertise of CK in the construction of large
infrastructure projects. Moreover, the two major shareholders, i.e. CK with
35.1% stake and Mitsui Water Holdings (Thailand) Co., Ltd. with 25.88% stake
have shareholding in the Company in a similar proportion, hence ensuring check
and balance. In addition, if Mitsui Water still holds shares more than 25%, it
is entitled to vote on any key issues of the Company. It is in this regard
difficult to transfer any vested interest to any related party.
Moreover, we have been informed from the Company's management that
in the construction contract business that for such kind of contractor work
for the Company, no other contractors in the industry will join in the bidding
in competition with CK for the contract from the Company because they do not
want to disclose their bidding price to competitor.
4. Fairness of Price and Conditions of Transaction
After reviewing the information and documents obtained as well as other
relevant information, our opinion is as follows:
4.1 Appropriateness of the price
4.1.1 Price and budget control by specialized team
Since January 2007, the Company has hired Expert Technologies
Limited and Sullivan Associates Company Limited as consultant to conduct
survey, review and prepare terms of reference, as well as preparation for
recruiting the project manager. In January 2008, the Company engaged Thai MM,
which is a member company in Mott MacDonald group which owns such website:
www.mottmac.com and having over USD 1.5 billion worth of transactions in 120
countries worldwide as well as 14,000 manpower, to handle management,
engineering and development as well as provision of consultancy in respect of
several industrial sectors, e.g. transportation, energy, construction, water
resource and environmental study and conservation, and industry and
telecommunication, as the project manager. It has been tasked with the study,
set strategy, review engineering requirements, and prepare documents and
criteria in selection of contractors. There are procedures set for invitation
of prospective contractors to submit proposals (only those related to civil
construction to be mentioned herein by the IFA as it is associated with the
connected transaction), selection, negotiation in details, and conclusion of
the final price, as follows:
Date Salient points of bidding for civil construction work
between the Company and CK
29 July 08 The Company issued a letter inviting CK to undertake civil
construction considering that CK has experience in the civil
construction of the tap water production and distribution plant in
Nakhon Pathom and Samut Sakhon provinces before, and has expertise
in infrastructure projects.
30 July 08 Thai MM worked out and concluded civil construction budget for the
Company in an amount of Bt. 663,419,480 (excluding VAT).
8 Sept 08 CK submitted civil construction proposal to the Company with total
contract value of Bt.675,004,000.00 (excluding VAT).
3 Oct 08 The Company together with Thai MM issued a letter to CK requesting
its additional explanation on certain technical issues under the
proposal submitted on 8 Sept 08.
7 Oct 08 The Company issued a letter to CK indicating that the price
proposed by CK on 8 Sept 08 was still higher than the civil
construction budget worked out by Thai MM, and requesting it to
review the price and resubmitting it to the Company by 10 Oct 08.
8 Oct 08 CK resubmitted the contract price at Bt. 655,000,000.00 (excluding
VAT) after the adjustment.
10 Oct 08 The Company issued a letter to CK informing it that the proposed
price of Bt. 655 million was still higher than the Company's
internal budget. However, to enable the construction to be
undertaken in line with the timeframe set, the Company in
collaboration with Thai MM made changes to the project
specifications in some areas, but with production efficiency still
maintained, such as downsizing the construction work of water tank
at the bulk transmission plant, adjustment of civil works at
Buddhamonthon water distribution station, etc. CK was requested to
consider such changes and resubmit the price to the Company by
13 Oct 08.
15 Oct 08 CK proposed the final price to the Company with total contract
value of Bt. 638,926,000.00 (excluding VAT).
17 Oct 08 CK issued a letter confirming the proposed price and informing the
Company of the installment payment method.
From the developments briefed above, and with meetings with the Company's
executives, we would like to clarify the roles and responsibilities of Thai MM
for this expansion project. Thai MM has no duty like a price appraiser of
assets, such as property, which will appraise the existing assets, e.g. land,
building, plant and machinery and equipment, to figure out the market price or
the replacement price of that asset item. Thai MM has the duty as project
manager or a coach for the Company from the date of the project study, design,
budget planning, selection of contractor until conclusion of construction and
contractor price. It has to coordinate with the Company staff in inspection of
the construction work for each payment installment until the plant is ready
for production of tap water.
For the above reasons, we believe that, in respect of consideration for the
construction work payable by the Company to CK, the management has made
negotiations under the hiring practice and in the normal course of business
operations (we consider from correspondence between the Company and CK and the
confirmation from the Company's engineers that the production efficiency still
maintained even thought there are some changes to the project specifications
in some areas), as well as with due consideration of the price reasonableness
and project efficiency. The final price is lower than the price first proposed
by CK by Bt. 36,078,000 or 5.34% of the first price proposed. The final price
is also lower than the budget worked out by Thai MM by Bt. 24,493,480 or 3.69%
of the budget.
4.1.2 Analysis of the rate of return
The discounted cash flows (DCF) approach will be proper to
apply only when:
1) The financial projection takes into account the economic
profit to be generated by such business activity, and
2) The valuation is on the going concern basis, with the
factors influencing the business profitability being projectable on definite
and reasonable gounds.
The assessment of the net present value of the future cash flows of the
water business expansion project will reflect the present value of the project
under the policy of normal business operations and management as in the past.
Thus, most assumptions are set based on the financial ratios and data actually
occurred in the past together with the operational plan and/or future policy
of the Company.
The principles used in the assessment of the net present value of the
future cash flows of the project adopted by the IFA for the calculation are as
below:
1) Projected cash inflows during January 1, 2009 until 2034 which is
the expiry year of the PSA between the Company and PWA (existing PSA). The
assumption for such period does not take into account the right to purchase of
the water business when the concessionaire has operated until the middle of
the concession term.
(more)